DATE | COMPLAINT NO. | DECREE | ACTION SUMMARY | CASE NAME |
6/12/2009 | 101-2011 (Den) | Final Order | License Suspended | Frank E. Chamberlein t/a Custom Exteriors and Remodeling, LLC |
12/4/2008 | 08-1368 | Final Order | $250 Civil Penalty and Reprimand | Glenn Bailey t/a DB Flatworks, Inc. |
12/3/2008 | 06-234 | Proposed/Final Order | $5,256.56 Guaranty Fund Award | John Sibiga t/a Whispering Valley |
6/22/2008 | 08-1164 | Proposed/Final Order | $20,000 Guaranty Fund Award | Michael Savosik |
4/7/2008 | 09-1005 | Proposed/Final Order | $13,027.66 Guaranty Fund Award | Robert Gilliam t/a RL Construction, LLC |
2/28/2008 | 09-721 | Final Order | Guaranty Fund claim dismissed | James G. Blair t/a Blair Construction, LLC |